Alabama Department of Transportation
Special DistrictAL
Posted
Oct 9, 2026
Nov 6, 2026
Constructing the Intersection Improvements RFP
Work includes 112 SY removing concrete driveway, 33 SY removing concrete pad, 359 SY removing concrete slab, 182 LF removing pipe, 462 LF removing guardrail, 4 EA removing guardrail end anchor (all type), 2 EA removing inlets (partial), 2 EA mailbox reset, single, 2,372 CY unclassified excavation, 1,790 CY borrow excavation (loose truckbed measurement), 500 Ton borrow excavation (underwater embankment), 62 CY structure excavation, 37 CY foundation backfill, commercial, 1,100 SY geosynthetic reinforcement for soft soil stabilization, type 2, 1,100 SY crushed aggregate base course, type b, plant mixed, 6" compacted thickness. See attached file.