South Utica Water Main Rehabilitation
Posted
Oct 1, 2026
Oct 15, 2026
Install cured in place pipe (CIPP) lining for approx. 525 LF of existing water main consisting of a mixture of 8" concrete lined ductile-iron pipe and 6 cast iron pipe, located in the City. Prior to the installation of the CIPP, the Contractor will clean and inspect the pipe. The project will require continued domestic service throughout the duration of the work for two residential parcels located along Alma Court. The Contractor will reinstate all services, hydrants and valves upon completion of liner curing. All subsequent work involved in the project including but not limited to; bypass flowing, traffic control, compaction, excavation backfill, site restoration including topsoil/seed, pavement, concrete, etc.; coordination; and service replacement tracking/documentation.